Gwarinpa GIS Substation Project
Project Overview
Design, construction, and commissioning of a state-of-the-art 132/33kV Gas Insulated Substation (GIS) in Gwarinpa, Abuja to address growing electricity demand in the metropolitan area.
Client
Transmission Company of Nigeria (TCN)
Location
Gwarinpa, Abuja
Duration
18 Months
Value
₦2.8 Billion
Challenges & Solutions
Urban Space Constraints
Limited space in densely populated area required compact GIS technology instead of conventional AIS.
Environmental Considerations
Implemented advanced environmental protection measures and noise reduction systems.
Technical Complexity
Deployed specialized engineering team with GIS technology expertise and rigorous testing protocols.
Project Gallery
Project Results
300MVA
Increased Transmission Capacity
50%
Space Saving vs Conventional AIS
250,000+
Households Served
0
Lost Time Injuries